Penn
State Chooses Infrared Heating
and Cross Ventilation for New Indoor Track Facility
Penn
State University opened its newest sports facility in the summer of 1999.
The new Indoor Track Facility replaces a outdated facility that was demolished
to make room for Joe Paterno's new football training facility. The building,
named Multisports Facility, contains two portions, the Box and the Program
Building. The 115,000 square foot Box houses the 220 meter track with
hydraulically banked curves, an Astroturf field, weight training facility
and the spectator grandstands. The Program Building contains the public
spaces and locker room facilities.
Architect NBBJ
of Columbus, Ohio teamed with Parfitt/Ling Consulting Engineers of State
College, Pennsylvania and construction manager Barclay White of Pennsylvania
to undertake the project under a fast track scenario. When the preliminary
project budget was in question during the schematic phase of the project,
the Engineer replaced the all-air mechanical system with a cross ventilation
system for cooling and an infrared radiation system for heating. The shift
in mechanical design strategy substantially reduced the mechanical system
costs as well as the mechanical room space requirement. The alternate
design resulted in both mechanical and general construction cost savings.
Cross
Ventilation
The building
was slated for a valley location below Beaver Football Stadium and Bryce
Jordon Basketball Arena. Prior to developing the arena and the indoor
track, this site was used for kite flying. The wind carried the kites
from the high points of this site towards Jeffrey Field, the outdoor track.
The Engineer took advantage of his knowledge of the prevailing wind direction
and the profile of the building to develop a cross ventilation strategy.
The Architect
designed a stainless steel asymmetrically curved roof over the track and
the field. The roof rises from a height of 35 feet on the west side to
a high point 45 feet above the track near the midpoint. At the east façade,
the roof is slightly lower than the high point. This profile in conjunction
with the building being sited perpendicular to the prevailing wind provided
an opportunity to cross ventilate the Box. Twenty air changes per hour
were designed to be delivered through 8' by 8' louvers on the west façade,
located on the upper and lower concourses behind the spectator seating.
On the higher east façade, sidewall propeller fans are placed in
the center of each twenty-five foot bay. The nineteen prop fans and the
inlet and outlet dampers are controlled in three stages in response to
indoor temperature. Mechanical cooling is provided only to the Program
Building.
Infrared
Radiant Heating
Given
the large volume of the Box and PSU's successful experience with infrared
radiant heating in Holuba Hall, the 117,000 square foot indoor football
practice facility, Roberts-Gordon Co-Ray-Vac heaters were selected as
the sole heating system for the Box. Infrared radiant heaters heat the
floor and the occupants of the building from 35 feet above the track.
The box utilized 3,500 feet of radiant heaters in nine arrays essentially
zoning the track separately from the spectator stands. These heater arrays
allow the facility to satisfy the different comfort requirements of event
participants and the spectators.
The Co-Ray-Vac
system consists of a series thirty four 100 MBH gas burners installed
in steel tubing. Reflectors are mounted above the tubing to direct the
radiant energy to the floor. The installation resembles a continuous array
of fluorescent light troffers. To protect the reflectors from damage and
stray sneakers,and other flying projectiles, a protective cage was provided
for the full length of all the heaters. Moses Ling worked closely with
the manufacturers representative, Dave Herrmann of Herrmann Associates,
Inc in Pittsburgh, PA to finalize the infrared design.
On the upper concourse behind the spectator stands, individual Caribe
infrared heaters were placed directly in front of the inlet louvers. The
modular Caribe heaters are eight feet in length and 30mbh each. Placing
the Caribe heater directly in front of each 8' by 8' grille raised the
surface temperature of the grille, providing an acceptable Mean Radiant
Temperature for the walkway adjacent to the air intakes.
Outside
Air System
Controlling
the temperature of the incoming air was not possible in the 18 inches
of wall thickness allowed for the natural ventilation intakes. Consequently,
two indirect gas fired Customaire air-handlers and a large round spiral
duct were installed to provide 20,000 cfm heated ventilation air to the
box. One of the Customaire unit also served to heat the storage and lower
concourse area.
Program
Building
The
Program Building contained the office, concession stand, locker room and
sport medicine functions. This portion of the building is air-conditioned
by a third Customaire unit with a Trane air-cooled chiller.
There are large
public washrooms to accommodate the 1200 spectator occupancy load. Locker
room and toilet exhaust air volumes were calculated based on the floor
area of these large rooms. It was recognized that the occupancy load would
seldom reach the design level. Therefore, the ventilation systems for
the Program Building were designed with two levels of operation, the lower
ventilation level for normal occupancy and a higher level for event days.
Successful Project
Penn
State's Multi-sport Facility has been in operation for one year. In its
inaugural season, Big Ten track meets were held. The facility also hosted
the PIAA state track finals. This spring the facility housed the opening
and closing ceremonies for the Pennsylvania Special Olympic Games. The
facility recently treated the National Governor's Association conferees
to a Penn State style tailgate. The Centre Daily Times reported Neighboring
New Jersey Governor Christine T. Whitman, on her first trip to Happy Valley,
said she relishing every minute of the tailgate. "This is fabulous,
very nice," Whitman said of the multi-sport facility. "It's
very state-of-the-art, but then again (Penn State) produces some state-of-the-art
athletes," she said. |
|